Project update: P5 (CVC) parking structure critical construction repairs
September 23, 2021 //
FOUND IN: Updates & Resources
Please be advised that critical repairs associated with the P5 (CVC) Parking Structure continue to progress.
Here’s what you need to know if you park in the area:
- Gold and Patient/Visitor parking spaces, with the exception of approximately 10 Patient/Visitor spaces for construction staging, should reopen by the end of this week.
- At the end of this week, the project team is expected to start applying a waterproofing layer within the Phase 1 work area (lane adjacent to the CVC main entrance). This is heat-applied and can have a strong odor, but will be done in the open air and is not dangerous.
- Early next week, the team is scheduled to start pouring the concrete topping slab for the Phase 1 area. Concrete trucks will stage along East Ann Street within the cutout for the Pavilion at U-M Health site, and concrete will be wheeled over to the site. A temporary sidewalk closure along the north side of East Ann will support this work and flaggers will be present.
- Once the concrete work is finished in the Phase 1 area, the project will proceed to work on the outer lanes of the CVC circle drive.
The project is targeting an early November completion date (please note that conditions and weather can impact the schedule).
Thank you for your patience and understanding during these critical repairs.