Update: Catherine St. parking structure facade repairs

April 13, 2021  //  FOUND IN: Updates & Resources

Please be advised that facade repairs to the Catherine St. parking structure began on Monday, April 5, and are planned for completion by the end of the month (weather permitting). 

The project is now in Phase 2, which involves repairs to the north face of the structure.

  • A sidewalk closure along the south side of Catherine Street will be in place and pedestrians will be detoured during this phase.  
  • While the contractor is working over the Catherine Street vehicular entry/exit (on Wednesday, April 14 and Thursday, April 15), this access will be temporarily closed between morning and afternoon peak times (approx. 9 a.m. – 3 p.m.).

In Phase 3, facade repairs will occur on the west face of the structure. The sidewalk that runs along the west side of the structure will be closed and pedestrians will be detoured.