Please be advised that facade repairs to the Catherine Street Parking Structure are scheduled to begin on Monday, April 5, and extend until Tuesday, April 20. This work completes a project initiated last construction season.  

Approximate dates for phasing are noted below and may be adjusted for any weather-related impacts:

  • Phase 1 (Monday, April 5-Thursday, April 8): Facade repairs will occur on the east face of the structure.
  • Phase 2 (Friday, April 9-Wednesday, April 14): Facade repairs will occur on the north face of the structure. A sidewalk closure along the south side of Catherine Street will be in place and pedestrians will be detoured.  
    • While the contractor is working at the northeast stair/elevator tower (approx. 2 days), this tower will be closed (approx. 8:30 a.m.-3:30 p.m.) and pedestrians will be directed to enter/exit via the structure’s west access.
    • While the contractor is working over the Catherine Street vehicular entry/exit (approx. 2 days), this access will be temporarily closed between morning and afternoon peak times (approx. 8:30 a.m.-3:30 p.m.).
  • Phase 3 (Thursday, April 15-Tuesday, April 20): Facade repairs will occur on the west face of the structure. The sidewalk that runs along the west side of the structure will be closed and pedestrians will be detoured.